TIME: 10AM
STEP 1: PREPARATION & GRINDING
We start by diamond grinding the concrete base. Dust is minimized by having all grinders hooked up to vacuum systems.
Meticulous about every detail
STEP 2: CONCRETE RESTORATION
Menders and Fillers are used to fix all of the pits and cracks before the process begins.
The Foundation
STEP 3: BASE COAT & CHIP
Our 100% solids, self-priming pure Polyurea basecoat is mixed and applied. Immediately after the basecoat application, the chip is generously broadcast by hand, providing both color and texture to the floor.
Needs to Cure
STEP 4: SET UP TIME
Setup times are typically within one (1) hour after application.
STEP 5: SCRAPING
Once the basecoat is fully cured, we spread the flakes. The floor is then scraped and vacuumed to remove any loose or vertical standing flakes.
Each step is the difference with our floors
STEP 6: TOP COAT